Award notice · Contracts Finder
A182 Bridge Maintenance Phase 2
Part of A182 Bridge Maintenance Phase 2.
A195 Princess Anne Interchange - Removal of existing surface and waterproofing, concrete repairs to parapet upstands, bridge decks, abutments, edge beams and bearing shelf areas. Replacement of existing parapets, renewal of bridge joints and reinstatement of waterproofing system and surfacing. Subway A182, Bonemill-Fatfield - Replacement of existing central expansion joint located in top of box section. Footbridges A182 East and West Slip Roads - Concrete repairs to parapet upstands, soffits and piers, blasting and repainting of existing parapets, removal of existing waterproofing and…
- Procurement
- A182 Bridge Maintenance Phase 2
- Published
- 24 Feb 2023
- Status
- complete
- CPV
- 45221100 — Construction work for bridges
- Tender period
- — – 10 Feb 2023
Awards
Other notices in this procurement
This is the only notice on record.
FAQs about this notice
What type of notice is this?
This is a award notice published via Contracts Finder on 24 Feb 2023.
Which procurement does this notice belong to?
It is part of "A182 Bridge Maintenance Phase 2", published by Sunderland City Council.
Has this notice resulted in an award?
1 award is recorded on this notice, including to Thomas Armstrong (Construction) Ltd.